Assignment 2-Project Management
Watch the video below. It will help you solve the problem:
Use the data below to create a network diagram and identify the critical path. What will be the total project duration?
Use the excel file for your submission.
Task |
Duration |
Predecessor |
A |
5 |
Start |
B |
8 |
A |
C |
3 |
B |
D |
4 |
A |
E |
5 |
C |
F |
7 |
C |
G |
6 |
D,E |
H |
8 |
F |
I |
6 |
G |
J |
4 |
H,I |