The purpose of this assignment is to practice schedule and cost variance. To do this, complete Ch. 13 Exercise #1 from Larson & Gray. Submit your answers in an APA-formatted Word document containing your name, course number/section, professor’s name, and assignment due date.
This is question #1:
1. In month 9 the following project information is available: actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project.